Sewer

Waste Water Capacity

  • The Oneida County Department of Water Quality and Water Pollution Control guarantees 3 MGD capacity immediately, with the ability to increase to 5.4 MGD.

Wastewater Treatment Plant capacity

  • 40–48 mgd (seasonal).
  • Existing facility has capacity to accept 3 mgd of additional flow.
  • Sewer upgrades and reduction in infiltration and inflow necessary to handle flow from 2 major semiconductor facilities

Wastewater Infrastructure

  • Wastewater conveyed by gravity flow (no pump-station required).
  • 36” transmission main exists 4,600 feet from site.

Proposed Sewer Improvements:

  • Off-site:
    • 4,600 LF of 18” PVC from 36” main to project site.
  • On-site:
    • 8,780 LF of 8” PVC.
    • Construction of pre-treatment plant.