Plentiful Water
- Mohawk Valley Water Authority has capacity to supply water needs for two Semiconductor facilities with projected requirements of 6 mgd.
Potable Water
- Water Treatment & Filtration Plant, built in 1992, has current capacity for 32 mgd.
- Total current consumption is 19.5 mgd.
- This leaves 12.5 mgd in available water.
Water System Infrastructure
- Hinckley & Marcy Reservoirs.
- 16” & 24” transmission mains.
- Proposed 16” water main on Edic Road will be tapped on both transmission mains at Mulaney Road/Edic Road intersection.
Proposed Water Improvements:
- Off-site: Construction of 5,480 LF of 16” water main, metering and pressure reducing facilities along Edic Road.
- Project completion is less than 12 months from start to finish.
- On-site (estimates):
- Metering and backflow prevention vault
- 12” water main 8,930 LF.
- 8” water main 825 LF.
- 350,000 gal. Storage tank
- Fire Pump.
- Project Completion is less than 12 months from start to finish